Two planned UK datacentres to emit more carbon than ExxonMobil

Created at 25 Aug · 11:12 AM1 source↑ Market-relevant
IN SHORT

Analysis suggests two planned datacentres in England will produce over 4.5 million tonnes of carbon emissions annually, exceeding ExxonMobil's UK emissions. Critics warn this poses a threat to the UK's climate goals, while the government disputes the utilization assumptions.

Key Numbers

4.577m tonnesannual carbon emissions from two datacentres
3.9m tonnesExxonMobil UK emissions in 2023
1.3GWpower demand for the two datacentres
315datacentres in queue for UK grid connection
73GWdemand from datacentres in grid queue

Who's Involved

Foxglove
Non-profit group that conducted the analysis
ExxonMobil
Fossil fuel company whose UK emissions were used for comparison
Ember
Global energy thinktank providing ExxonMobil's emissions data
Tom Hegarty
Head of communications at Foxglove
Kierra Box
Campaigner at Friends of the Earth
Caroline Lucas
Former England and Wales Green party leader
Toby Perkins
Labour MP and chair of the Commons environmental audit committee
Oliver Hayes
Head of policy at Global Action Plan
Sam Hunter-Jones
Lawyer at ClientEarth
Department for Energy Security and Net Zero
Government department responding to the analysis

↳ Why This Matters

The projected carbon emissions from two planned datacentres significantly exceed those of a major fossil fuel company, raising serious concerns about the UK's ability to meet its legally binding climate targets and highlighting the growing environmental impact of the digital infrastructure sector.

Key facts

  • Two planned datacentres in England, Wapseys Wood and Quest Park, are projected to emit over 4.5 million tonnes of carbon annually.
  • This projected emission level exceeds ExxonMobil's 2023 UK emissions of 3.9 million tonnes.
  • Both datacentres are seeking to build their own on-site gas-fired power stations due to grid connection delays.
  • The analysis assumes a 100% utilization rate for the datacentres, a standard industry practice according to campaigners.
  • The government disputes the emission figures, stating the utilization assumption is inaccurate and that datacentre growth can align with climate targets.

Analysis by the non-profit group Foxglove indicates that two planned datacentres in England, Wapseys Wood in Buckinghamshire and Quest Park in Bedfordshire, will collectively produce over 4.5 million tonnes of carbon emissions annually once operational. This figure surpasses the 3.9 million tonnes emitted by ExxonMobil in the UK in 2023, according to the thinktank Ember.

These datacentres, which require substantial electricity for servers and cooling, are reportedly seeking to build their own on-site gas-fired power stations due to long waits for grid connections. Foxglove's calculation, based on government figures for electricity generation's carbon intensity, projects 4.577 million tonnes of emissions per year from these two projects.

A government spokesperson described the figures as misleading, challenging the assumption of 100% utilization from day one. However, campaigners like Tom Hegarty from Foxglove and Kierra Box from Friends of the Earth defended the projection, stating that the aim for datacentres is to operate at full capacity and that top-level predictions are valid.

Former Green party leader Caroline Lucas called the projected emissions 'absolutely horrifying,' while Labour MP Toby Perkins highlighted the analysis as a reminder of the environmental threat posed by datacentres without proper measures. Oliver Hayes of Global Action Plan suggested that accommodating this rapid datacentre growth within carbon budgets would necessitate stricter limits on other economic sectors. ClientEarth lawyer Sam Hunter-Jones argued that datacentre growth hinders the transition away from fossil fuels by consuming power that could otherwise replace them.

Concerns were also raised about the projects being fast-tracked through the nationally significant infrastructure project (NSIP) regime, which bypasses local planning authorities. Hayes viewed this as a 'very worrying sign' and an 'affront to local people,' suggesting it indicates a lack of seriousness about addressing datacentre emissions. Lucas echoed these concerns, stating the NSIP regime reduces local scrutiny.

The Department for Energy Security and Net Zero stated that datacentres are vital to the economy and that the government will enable their growth by building clean power.

Frequently asked questions

The analysis found that two planned datacentres in England will have higher UK carbon emissions than ExxonMobil's UK operations.

The Wapseys Wood and Quest Park datacentres are projected to produce over 4.5 million tonnes of carbon emissions per year when fully operational.

They are seeking to build on-site gas-fired power stations due to long wait times to connect to the UK's electricity grid.

The government called the figures misleading, disputing the assumption of 100% utilization and stating that datacentre growth can align with climate targets through clean power development.

What Happens Next

01The Commons environmental audit committee is leading an inquiry into the environmental impact of datacentres.
02The government is expected to provide further analysis on how datacentre rollout can fit within the seventh carbon budget.

How It Developed

Analysis reveals two planned datacentres will exceed ExxonMobil's UK carbon emissions.
The Wapseys Wood and Quest Park datacentres are seeking to build on-site gas-fired power stations.
Foxglove calculated these projects will produce 4.577m tonnes of carbon emissions per year.
ExxonMobil emitted 3.9m tonnes in 2023, according to Ember.
A government spokesperson called the figures misleading, disputing the 100% utilization assumption.
Campaigners and MPs expressed alarm over the projected emissions and the fast-tracking of these projects.
The government stated its analysis shows datacentre growth can fit within carbon budgets with clean power.

Sources

T1
Two planned datacentres will have higher UK carbon emissions than ExxonMobil, analysis findsThe Guardian

Related Stories

Albanese to push for national datacentre rules amid climate concerns
24 Aug · 2:16 PM
AI Startup Emerald AI Targets Data Center Power Demand
25 Aug · 11:46 AM
UK and Ukraine Forge AI Partnership Using Battlefield Data
24 Aug · 6:26 PM
AI data centers drive demand for new solid-state transformer technology
24 Aug · 9:36 PM
AI Founders Launch Physics Model After Rejecting Bezos's Project Prometheus
25 Aug · 10:05 AM