A Tasmanian council reluctantly approved plans for a 288 MW datacentre, facing strong community opposition over energy use and AI concerns. The decision comes just before national standards for large datacentres are set to be legislated.

Key Numbers

288 megawattdatacentre capacity approved in Tasmania
6-1council vote to approve datacentre
6,000signatures on petition against datacentre
300+submissions on datacentre application
14 daysappeal period for datacentre decision
225datacentres in development across Australia
$1.1bndatacentre campus value in Victoria
366MWdatacentre campus capacity in Victoria

Who's Involved

George Town council
Tasmanian council that approved a datacentre proposal
Firmus
Australian developer planning the datacentre
Anthony Albanese
Australian Prime Minister announcing national datacentre standards
Heather Ashley
Councillor who described the decision as difficult
Winston Mason
Councillor who cited planning rules for the decision
Anne-Marie Bastian
Initiator of the petition against the datacentre
Oliver Curtis
Co-founder of Firmus
Sarah Hanson-Young
Greens senator and chair of the datacentres inquiry
Zerra DC
Company behind a datacentre proposal in Victoria

↳ Why This Matters

This decision sets a precedent for how local councils will handle datacentre proposals amid growing community concerns and ahead of new national regulations, potentially influencing the pace and location of AI infrastructure development across Australia.

Key facts

  • George Town council in Tasmania approved a 288 MW datacentre proposed by Firmus.
  • The approval was met with significant community opposition and was described as reluctant by councillors.
  • Concerns raised by locals included energy consumption and the implications of AI technology.
  • The decision precedes the federal government's planned introduction of national datacentre standards.
  • The federal government intends to legislate a regulatory framework for large datacentres early next year.
  • Victoria's Environment Protection Authority has issued its first objection to a datacentre proposal.

The George Town council in Tasmania has approved plans for a 288-megawatt datacentre by developer Firmus, despite significant community opposition and concerns over energy use and AI. The council voted 6-1 to approve the project, with councillors expressing reluctance and stating they had to adhere to existing planning regulations.

Locals had raised objections, citing potential environmental impacts and the need for federal oversight, pointing to Prime Minister Anthony Albanese's recent announcement of a forthcoming national regulatory framework for large datacentres. The federal government plans to introduce mandatory standards for energy, water, and land use, designed to complement, not duplicate, state and territory processes.

Despite the community's calls for a moratorium or retrospective laws, the council felt bound by current guidelines. Firmus welcomed the decision, stating the project would proceed and that their facilities are designed for energy efficiency and responsible water use. Meanwhile, Victoria's Environment Protection Authority has issued its first objection to a datacentre proposal, citing noise and cumulative impact concerns.

The Australian Energy Market Operator reported 225 datacentres are currently in development nationwide, highlighting the growing demand and the urgency for regulatory clarity.

Frequently asked questions

The community raised concerns about the datacentre's energy consumption, the implications of AI technology, and the lack of comprehensive federal regulation.

The councillors stated they were bound by existing planning guidelines and regulations, and could not wait for future federal rules to come into effect.

The government plans to legislate a nationally consistent regulatory framework with minimum mandatory standards for energy, water, and land use for large datacentres.

Yes, Victoria's Environment Protection Authority issued its first objection to a datacentre proposal due to potential noise risks and cumulative impacts.

What Happens Next

01Objectors have 14 days to appeal the George Town council's decision.
02The federal government plans to legislate national datacentre standards from early next year.
03Firmus will proceed with design, procurement, and construction planning for the datacentre.
04Zerra DC will work with acoustic consultants regarding EPA feedback on its Victorian proposal.

How It Developed

George Town council voted to approve Firmus's 288 MW datacentre proposal.
The decision faced significant community opposition, with a petition and numerous submissions against the project.
Locals cited concerns about energy use and AI, urging the council to wait for new federal regulations.
Prime Minister Anthony Albanese announced plans for a nationally consistent regulatory framework for large datacentres.
Councillors stated they had to apply current planning rules, not future ones.
Firmus welcomed the approval and plans to proceed with the project.
The Greens called for a moratorium on new AI datacentres until federal rules are in place.
Victoria's EPA issued its first objection to a datacentre proposal over noise and site layout concerns.

Sources

T1
‘Reluctant’ approval for Tasmanian datacentre sets marker for national battleThe Guardian

Related Stories

US communities unite across party lines to oppose AI data centers
26 Aug · 4:31 AM
Ohio's 'World's Largest Datacenter' Sparks Hope and Environmental Concerns
26 Aug · 12:06 PM
Community backlash, regulatory hurdles challenge data center expansion: AirTrunk CEO
26 Aug · 9:31 AM
Grafana Labs Surpasses $600 Million ARR Amid AI Deployment Boom
26 Aug · 9:11 AM
Bill Gates proposes 'human reserved' jobs amid AI concerns
26 Aug · 10:41 AM