Key facts
- NRG Energy said a large Texas data center can avoid $33.4 million in transmission costs by staying off the grid one hour a year.
- PJM Interconnection's independent monitor attributed $29.4 billion in added power-system costs to data center growth.
- Google told Texas regulators in an August filing it would pay about $1.4 billion in transmission charges over 20 years under one scenario.
- Andrew Major of the Virginia State Corporation Commission said in July testimony residential customers paid 48% of a transmission project serving a data center.
- Dominion Energy said its new rate class, mostly data centers, requires 14-year contracts and minimum payments for unused power.
- The Data Center Coalition said peak shaving lets grid operators plan on reductions, so less new capacity and transmission must be built.
US data center operators and other large power users can cut millions of dollars from electricity bills by sharply reducing grid power use during a handful of crucial hours each year, a practice known as peak shaving, Reuters reported on November 17, 2026. The practice is legal and encouraged under US power-market rules and state tariffs, but critics say it lets large users reduce their share of grid costs in ways households cannot.
NRG Energy, based in Houston, said a large data center in Texas can avoid $33.4 million in transmission costs by staying off the grid for one hour a year, either by cutting power use or firing up backup generators. Grid costs are allocated in part according to electricity use during periods of highest demand, and operators do not post summer peak hours in advance, so large customers hire forecasters to predict them.
PJM Interconnection's independent monitor said rapid growth of energy-hungry data centers has already increased power-system costs by $29.4 billion across the grid, charges that utilities pass on to electricity customers. The Data Center Coalition said in a statement that grid operators can count on peak-shaving reductions in planning, so less new capacity and transmission must be built, which it said lowers costs for all customers.
Google complained to Texas utility regulators about a scenario in which it would pay about $1.4 billion in transmission charges over 20 years, according to an August filing with the Public Utility Commission of Texas. Andrew Major, a lawyer at the Virginia State Corporation Commission, said in July testimony that residential customers paid 48%, the largest share, for a transmission project serving a data center.
Dominion Energy, whose territory includes Virginia, said it created a new rate class mostly consisting of data centers, requiring 14-year contracts and minimum payments if the power is not used. Bailey Wells, a residential customer in Spring, Texas, said her monthly electric bill climbed to nearly $600 in summer 2026, against a previous summer high of about $500. Will Baker, head of market development at Everyday Electric, which provides power services for homes, said a factory has an energy manager, interval data and a capacity charge that rewards every kilowatt it shaves, while a household has none of those.