Key facts
- The 5th US Circuit Court of Appeals said MARAD's record of decision violated the Deepwater Port Act's one-port-per-application-area rule.
- The court said Texas GulfLink's properly designated application area would have intersected Enterprise Products Partners' Sea Port Oil Terminal project.
- Sentinel senior vice president Bruce Heine said the license has not been suspended or terminated and the project remains on track for a fourth-quarter 2028 operational date.
- A source familiar with the matter said Sentinel cannot continue with the offshore project on the current license.
- Sentinel said in its stay motion that it plans to petition the Supreme Court and that two other pending deepwater ports may need redesignation.
- Texas GulfLink is designed to load a supertanker with about 2 million barrels of oil per day, according to the report.
A court ruling has put at risk the license for Sentinel Midstream's $2.1 billion Texas GulfLink deepwater crude oil export project off the Texas coast, according to an environmental group that petitioned the court. The ruling took effect on October 30.
The 5th US Circuit Court of Appeals in August voided the federal record of decision for Texas GulfLink, finding that MARAD's approval violated the Deepwater Port Act's requirement that only one deepwater port be approved per application area. The court said Texas GulfLink's application area, when properly designated, would have intersected Enterprise Products Partners' Sea Port Oil Terminal project. MARAD had approved Texas GulfLink with conditions in its 2025 record of decision, and Sentinel received its license in January 2026. Sentinel made a final investment decision in May and began construction.
Michael Brown, counsel for the petitioners, said on Wednesday: "The Court's decision is clear: it vacated the record of decision that was the foundation of GulfLink's license. Now, MARAD has to revoke or suspend that license." Better Brazoria Clean Air and Water said in a press release this week that construction cannot continue without a federal deepwater port license. MARAD said it was disappointed with the outcome and continues to pursue all avenues to achieve the President's vision of American energy dominance.
Sentinel said its license has not been suspended or terminated. Bruce Heine, a senior vice president at Sentinel, said Texas GulfLink remains on track for a fourth-quarter 2028 operational date and that there are multiple paths to address the statutory concern without disrupting construction or the overall schedule. He said site development and improvement activities are underway at the Jones Creek onshore terminal facility ahead of tank construction, and that major long-lead equipment and pipe have been purchased and key construction contracts executed.
In its motion last month to stay the court mandate, Sentinel said the license expressly incorporates the record of decision as a compliance standard, so voiding the record of decision exposed the license to suspension or revocation by MARAD and prevents construction of offshore components. The company said then that "given the uncertainty of its ROD and license, Texas GulfLink will not commence construction of the deepwater port under the current posture, even if the mandate is stayed." It said it plans to petition the Supreme Court and that two other pending deepwater ports with similar application areas will likely require redesignation.
A source with knowledge of the situation said the company could not continue with the offshore project on the current license. If Sentinel is required to resubmit its application, it would have to await a new record of decision and license; securing approvals took nearly seven years last time, while MARAD recently issued a deepwater project application license in 410 days, nearly 3.7 years faster than the historical average. Texas GulfLink is to be situated about 30 miles off Freeport, Texas, and aims to fully load a supertanker with about 2 million barrels of oil per day.