Key facts
- The first data center permit after Texas lifted its freeze appears to have gone to SpaceX for a $24 billion Starbase project, Politico reported.
- ERCOT's large-load queue stands at 474 gigawatts, more than five times the grid's all-time peak demand of a little over 90 gigawatts.
- ERCOT's chief executive, Pablo Vegas, said in April 2026 the forecast ran higher than the growth he expected.
- PUC chair Thomas Gleeson said on a June 2026 podcast that a lot of the projected load will not actually come to Texas.
- ERCOT told the commission on November 5, 2026 that 93% of companies had answered its information requests.
- Abbott's press secretary, Andrew Mahaleris, said no permits have been approved.
The Texas Commission on Environmental Quality resumed normal permit review on November 16, 2026, after being told that ERCOT, the grid operator, had finished gathering community-impact information for its audit, Politico reported. Governor Greg Abbott's September letter had tied the pause to that audit, and ERCOT's reports are not targeted until December 10, so the restart came weeks early.
The first data center permit Texas issued after lifting its freeze appears to have gone to SpaceX, for a $24 billion project at Starbase, according to Politico. Abbott effectively froze new data center grid connections in August, then told the agency in September to stop issuing air and other permits for the same projects. Within days the agency had mailed preliminary approvals for three gas-fired power projects meant to supply data centers, according to a FracTracker and Public Citizen report. "No permits have been approved," Abbott's press secretary, Andrew Mahaleris, said.
Most of what gets called the boom is a number in a queue. ERCOT's large-load queue stands at 474 gigawatts, more than five times the grid's all-time peak demand of a little over 90 gigawatts. Thomas Gleeson, who chairs the Public Utility Commission, said on a podcast in June that the projections are extremely high and that "a lot of that load will not actually come here." ERCOT's chief executive, Pablo Vegas, had said in April that the forecast ran higher than the growth he expected. Senate Bill 6, signed last year, now requires applicants to prove they control a site and to cover most of the grid upgrades they need, and it makes them accept being cut off during an emergency.
The audit is supposed to sort the real from the hypothetical. ERCOT told the commission on November 5 that 93% of companies had answered its information requests, and the full findings are not public. The law firm Gibson Dunn lists December 10 as the target for ERCOT's reports and December 17 for the commission's meeting on them.