Key facts
- Applied Digital did not name the hyperscaler tenant behind the 150 MW lease.
- Applied Digital said the lease carries higher pricing and improved commercial terms than its prior leases.
- Applied Digital said total contracted base-term lease revenue now exceeds $41 billion, or about $100 billion with renewals.
- About 75% of contracted base-term lease revenue is tied to investment-grade customers, Applied Digital said.
- CFO Saidal Mohmand said the build will be financed through the company's $5 billion equity partnership with Macquarie Asset Management, then project financing.
- Delivery of the capacity is expected to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals.
Applied Digital said on November 23 that it had leased 150 megawatts of critical IT capacity to an investment-grade hyperscaler it did not name, a deal the company expects to generate $5.4 billion in contracted revenue over an 18-year base term.
The lease can be extended to a total of 33 years and would be worth about $12.7 billion if all renewal options are exercised, Applied Digital said. The company said the agreement carries improved commercial terms over its prior leases, including higher pricing.
The deal follows a 15-year, 210 MW lease worth about $5.2 billion that Applied Digital signed in June at its Delta Forge 2 site. Applied Digital said its total contracted base-term lease revenue now exceeds $41 billion, or about $100 billion with renewals, and that about 75% of that base-term revenue is tied to investment-grade customers.
"We plan to finance this build through our established structure," CFO Saidal Mohmand said in a statement, citing the company's $5 billion equity partnership with Macquarie Asset Management, followed by project financing. Delivery of the capacity is expected to begin in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals.