Key facts
- Oracle said the financing outlined at its Investor Day, including vendor financing, is in place, in a post on X.
- Oracle and OpenAI plan 4.5 gigawatts of additional US data-center capacity beyond the initial Stargate site in Abilene, Texas.
- Oracle said its Abilene campus, where OpenAI's GPT-6 Astra was trained, is nearly complete.
- Oracle said its next gigawatt-scale campus in Shackelford County, Texas, is fully permitted.
- Oracle said handover of Nvidia's next-generation Vera Rubin racks is on track for the coming weeks.
Oracle said on November 20 that its infrastructure contract with OpenAI is fully funded following a final capital raise earlier in the month. The statement came in a post on X and followed investor scrutiny over how much capital Oracle would need to fund its expansion of AI data centers and its growing exposure to OpenAI.
Oracle said the financing it outlined at its Investor Day, including vendor financing, is in place, and that any further private discussions with vendors are additional options. Earlier in November the company announced a $20 billion capital raise, consisting of about $10 billion in stock and $10 billion in debt.
Oracle and OpenAI plan to develop 4.5 gigawatts of additional data-center capacity in the US, on top of the initial Stargate site in Abilene, Texas. Oracle said the Abilene campus, where OpenAI's GPT-6 Astra was trained, is nearly complete, and that its next gigawatt-scale campus in Shackelford County, Texas, is fully permitted. Handover of Nvidia's next-generation Vera Rubin racks is on track for the coming weeks, Oracle said.
Oracle shares rose as much as 3.3% in after-hours trading.