Key facts
- Of nearly 600 submissions, 595 opposed the project or asked for a delay until environmental hurdles were cleared, the filing said.
- Two submissions supported the Western Downs Digital Park and one was neutral, according to the filing.
- About one-third of submissions came from people living within 200 km of the site, the filing said.
- The project would have a planned computing load of 1.44 gigawatts, one of Australia's biggest, the filing said.
- Objectors mostly cited water use, electricity demand and prices, noise, road damage and pressure on housing, the filing said.
- The filing, lodged for developer Zerra DC, said a significant number of submissions raised reasonable matters on water, power, noise, roads, housing and scale.
A data centre planned in regional Australia with Anthropic as its anchor tenant drew overwhelming opposition from residents, according to a filing for the project. Of nearly 600 public submissions on the proposed Western Downs Digital Park, about 250 km (155 miles) west of Brisbane, two expressed support and one was neutral, the filing said. The remaining 595 opposed it or asked for a delay until developers cleared certain environmental hurdles.
The filing, lodged on behalf of developer Zerra DC, said a significant number of submissions raised reasonable matters regarding water, power, noise, roads, housing and the scale of the project. Representatives of Zerra and Anthropic were not immediately available for comment. About one-third of the submissions came from people who lived within 200 km of the site, the filing said.
Objectors mostly cited concerns about water use, electricity demand and prices, noise, road damage from construction traffic and pressure on housing. Before the project named Anthropic as its tenant on September 15, it had received five objections in a month, a log of public comments showed, with the rest arriving between then and November 11, when the local government stopped accepting submissions.
The project is on farmland and further from the suburbs, but with a planned computing load of 1.44 gigawatts it would be one of the country's biggest. The initial response is far from binding. Already in Australia, Goodman Group scrapped a roughly A$1.2 billion data centre planned for Sydney in September after a public backlash, while NextDC delayed a project in Melbourne amid resident concerns about energy use, triggering a shares selldown.
The filing was published the same week Anthropic made its stock market debut on Wall Street, pricing its initial public offering on November 18 in a deal that valued the company at around $1.5 trillion.