- NextDC chair Doug Flynn said the company does not intend to pursue new developments near residential properties.
- The M3 expansion in West Footscray was delayed after Jemena paused construction of new 22m power poles amid community protest.
- NextDC's share price dropped 40% during the backlash and has since recovered to over $9 per share.
- Rival Goodman Group bought a nearly 10% stake in NextDC.
- Shareholders issued a second strike against executive pay, but the motion to spill the board was resoundingly defeated.
- NextDC said it will set up a community consultative committee and a dedicated project website with defined response times.
NextDC will no longer pursue new datacentre developments near residential properties, chair Doug Flynn told the company's annual general meeting on Friday, November 20, 2026, after community backlash to an expansion in inner Melbourne. The company held its first annual general meeting since it was forced to delay the controversial expansion of its M3 site in West Footscray after power provider Jemena paused construction of new 22m power poles amid community protest.
The share price dropped 40% during the backlash and has since recovered to over $9 per share. Rival Goodman Group bought a nearly 10% stake in the business. Shareholders revolted against the company at the meeting, issuing a second strike against executive pay, but the resulting motion on whether to spill the board was resoundingly defeated on Friday.
Chief executive Craig Scroggie said it was his "hardest AGM" in 15 years and said he ultimately took responsibility for "delivery, power, planning, approvals, construction and community support". He said the community deserved to be heard earlier than they had been during the Jemena construction works. "M3 has certainly changed how we plan, build and operate alongside our neighbours," he said. "For more than 15 years we've built datacentres right across the country, and what earned trust then is not enough now. Community expectations have moved in the age of artificial intelligence and we must move with them."
NextDC said it will set up a new community consultative committee, including a standing forum for residents and local stakeholders, a dedicated project website and contact channels with defined response times for complaints and inquiries. Flynn said the M3 site in inner Melbourne had been an industrial site for 100 years and had petrochemical works on it before NextDC built the datacentre. He said the Jemena employee overseeing community engagement left the business. "They recognise that they were just charging ahead regardless of community. And they got a bloody nose. Unfortunately, we did as well," Flynn said. A Jemena spokesperson declined to comment but pointed to a September statement announcing its general manager for electricity networks had decided to step down.