- Grossi said the further extension to the original Yongbyon enrichment facility was externally complete by late October 2026.
- Grossi said the IAEA has observed indications the 5-megawatt reactor at Yongbyon probably continues to operate.
- The Yongbyon reactor is in its seventh irradiation cycle, after which spent fuel would be removed for reprocessing, Grossi said.
- A light-water reactor at Yongbyon has been operating since April 2026, Grossi said.
- Grossi gave no detail on the size or output of the new extension, saying only that it was externally complete.
North Korea has built an extension to its original uranium-enrichment plant at the Yongbyon nuclear complex, International Atomic Energy Agency Director General Rafael Grossi said in a statement to the agency's 35-nation Board of Governors on November 18, 2026.
Grossi said construction of the further extension began in mid-September 2026 and that it was externally complete by late October 2026. He did not elaborate. "The ongoing expansion of the DPRK's uranium enrichment programme remains a cause for serious concern," he told the quarterly meeting in Vienna.
Grossi said he had previously reported on the operation of enrichment facilities at Kangson and Yongbyon, the construction of an additional enrichment facility at Yongbyon, and the reported further expansion of North Korea's production of weapons-grade nuclear material. Kangson lies just southwest of Pyongyang, while Yongbyon, the larger site, is further north of the capital.
The IAEA has had no access to North Korea since Pyongyang expelled its inspectors in 2009 and now observes the country mainly using satellite imagery. North Korea, formally the Democratic People's Republic of Korea, has carried out several nuclear tests and appears to continue producing highly enriched uranium and plutonium, the two materials used to make the core of a nuclear weapon.
Grossi also said the agency had "observed indications" that the 5-megawatt reactor at Yongbyon, which North Korea uses to produce plutonium from spent fuel, probably continues to operate and is in its seventh irradiation cycle. After that cycle the spent fuel would be removed for reprocessing, he said. A separate light-water reactor at Yongbyon has been operating since April 2026, he added.