Key facts
- Honghua Group delivered two 3,000-horsepower AI-enabled rigs to an Abu Dhabi island for ADNOC, the report said.
- The transport from Zhangjiagang port to the island took 80 days, a record for a comparable Honghua overseas project.
- On March 10, 2026, a drone was shot down about 2 km from the island and jets passed about 20 meters above the platform.
- The two rigs completed 583 lifts by August 2026, and a third rig's derrick was raised, according to the report.
- Honghua said the rigs are 80% localized by parts and 90% localized in core intelligent systems.
Honghua Group, a unit of state-owned Dongfang Electric Group, delivered two AI-enabled drilling rigs to an artificial island in Abu Dhabi and raised the derrick of a third, according to a report by China Electric Power News published on November 28, 2026. The rigs, 3,000-horsepower units built for Abu Dhabi National Oil Company (ADNOC), had to transit the Strait of Hormuz into the Persian Gulf at a time when the report said shipping through the strait was restricted by regional conflict.
According to the report, Honghua's logistics coordinator Yang Xiaoli convened a coordination team in Deyang, Sichuan, in February 2026 after being told that the strait's shipping situation was tightening and the usual route was blocked. The team contacted shipping providers, insurers willing to underwrite war risk and local authorities, and found a vessel permitted to transit the strait, the report said. The full transport from Zhangjiagang port to the island was completed in 80 days, a record for a comparable Honghua overseas project, according to the report.
The report said the island work faced direct security incidents. On March 10, 2026, at 10 a.m., workers saw two columns of smoke from explosions about 10 km offshore; minutes later a drone was shot down about 2 km from the island by local air force fighter jets, and aircraft then passed about 20 meters above the working platform, signaling workers to move to a safe zone. Safety officer He Jun said the team activated its emergency plan and evacuated. Flights and vessels to and from the island were suspended for a period, the report said, and the team kept two emergency boats on standby around the clock and staged evacuation drills.
By August 2026 the two rigs had completed 583 lifts, the report said. Honghua said the rigs' OPERA operating system integrates AI-assisted drilling, friction testing and automated directional sliding, and that the machines are 80% localized by parts and 90% localized in core intelligent systems. ADNOC project manager Romains said the Chinese team was professional and reliable and ensured the equipment entered service on schedule, according to the report.