Key facts
- The CBO said the Navy's 2027 plan underestimates new fleet costs by billions, partly because some ship designs proved more complicated than expected.
- The CBO attributed much of the added cost to the Navy's decision to buy 15 large, heavily armed battleships, the proposed Trump-class warships.
- Senate appropriators proposed cutting to zero the $1 billion the Navy sought in advanced procurement for the Trump-class ships this fiscal year.
- Acting Navy Secretary Hung Cao told senators the Iran war was a strain on the Navy and that insuring a ship for one Strait of Hormuz passage had risen to $64 million from $54,000 a year earlier.
- Michigan senator Elissa Slotkin told the committee the Iran conflict is estimated to have cost the US $260 billion.
- Shipping traffic through the Strait of Hormuz was about 65% below pre-war levels, according to UK Maritime Trade Operations.
The Congressional Budget Office told Congress that the US Navy's 2027 shipbuilding plan underestimates the cost of its new fleet by billions of dollars, in a report dated November 21, 2026. The CBO said some ship designs proved more complicated than expected and that estimated costs of some ships were unrealistically low in earlier plans. Average shipbuilding costs would run $54 billion a year in 2026 dollars over 30 years, about 18% more than Navy estimates.
The CBO attributed much of the added cost to the Navy's decision to buy 15 large, heavily armed battleships, the proposed Trump-class warships. It said concentrating firepower in a few large ships would be at odds with the Navy's stated goal of distributing it among more ships. President Trump has said the warships would be 100 times more powerful than any previous US warship. Senate appropriators proposed cutting to zero the $1 billion the Navy sought in advanced procurement for the Trump-class ships this fiscal year.
The Navy wants to grow its fleet from 286 battle force ships to 381 over 30 years, outpaced in shipbuilding by China. At a Senate confirmation hearing on Wednesday, November 18, 2026, acting Navy Secretary Hung Cao said the Iran war was stretching the fleet's capacity. Cao told senators the cost to insure a commercial ship for a single Strait of Hormuz passage had risen to $64 million from $54,000 a year earlier.
Senator Richard Blumenthal told Cao the world is less safe because of the Iran war and that the Navy had been stretched beyond sustainable limits. Senator Elissa Slotkin said the conflict is estimated to have cost the US $260 billion. Shipping traffic through the Strait of Hormuz remained about 65% below pre-war levels, according to the latest weekly report from UK Maritime Trade Operations.
Since the Iran war began, ships have been deployed for 10 to 11 months, beyond the standard seven, and several have spent more than 300 days deployed. The USS Abraham Lincoln went 265 days at sea, the longest a Navy ship has gone without visiting a port. Cao disputed accounts of a mental health crisis aboard the Lincoln, saying eight reported suicide attempts were instead suicide mitigations, and dismissed a report that a sailor lost 45 pounds in six months because of a lack of food.
The USS George Washington returned from the Middle East on Wednesday, November 18, 2026, ending a period from August to November when the US had no aircraft carrier group in the Pacific, only the second such gap in two decades. Kevin Rowlands, journal editor at the Royal United Services Institute, told the Guardian the overstretch was critical but manageable for now, and that the US has zero spare capacity across its AUKUS, Indo-Pacific, NATO and Middle East commitments.