Key facts
- TEPCO found in September a problem with the strength of the concrete housing Unit 7 at Kashiwazaki-Kariwa.
- Unit 7 had been scheduled to restart by August 2029, a date TEPCO now must revise.
- Takeyuki Inagaki, superintendent of the plant, said it was too early to give a revised timeline.
- Inagaki said the contractor building the reactor housing has said the August 2029 date could slip by more than a year.
- TEPCO must meet Japan's counter-terrorism requirements, which require the facility to withstand a deliberate plane crash.
- Kashiwazaki-Kariwa has a nameplate capacity of nearly 8 GW, the largest of any nuclear plant.
Tokyo Electric Power Company will delay the restart of Unit 7 at its Kashiwazaki-Kariwa nuclear power plant in Niigata prefecture, the company said on November 26, 2026. The plant, the world's largest by nameplate capacity at nearly 8 GW, had been slated to bring the unit back online by August 2029.
The delay follows a problem TEPCO identified in September with the strength of the concrete construction housing the reactor. TEPCO must revise the construction and restart schedule to meet the counter-terrorism requirements of Japan's nuclear safety watchdog, which require the facility to withstand a deliberate plane crash.
Takeyuki Inagaki, superintendent of the Kashiwazaki-Kariwa station, told a media briefing on Thursday that it was too early to provide a revised timeline. He said the contractor that would build the structure to house the reactor had said the August 2029 restart date could slip by more than one year. "It will take time to determine the cause," Inagaki said, as carried by Bloomberg.
TEPCO restarted Unit 6 at the plant earlier in 2026, returning to nuclear generation after nearly 15 years following the 2011 Fukushima disaster. Before the meltdown, nuclear energy accounted for about 30% of Japan's electricity mix. The disaster prompted the closure of all reactors for safety checks; since 2015, Japan has restarted 15 of its 33 reactors, with 7 in the restart approval process.
The report said delays in reactor restarts could raise Japan's gas demand in the near and medium term, and that Japanese utilities may increase spot LNG cargo purchases in the coming weeks as higher electricity prices have made gas-fired generation profitable for the first time since the Iran war began.