Key facts
- SoftBank Corp. and Sharp Corporation will construct a large-scale AI data center at the former Sharp Sakai Plant in Osaka.
- The data center will occupy approximately 440,000 square meters, with a total floor area of 750,000 square meters.
- Initial power capacity will be 150 megawatts, with plans to expand to over 400 megawatts.
- Full-scale operations are targeted to commence in 2025, with construction starting in autumn 2024.
- SoftBank intends to use the facility for its generative AI development and offer it to external clients.
- Consideration will be given to utilizing clean energy sources to minimize environmental impact.
SoftBank Corp. and Sharp Corporation have signed a Memorandum of Understanding to construct a large-scale AI data center at Sharp's former LCD panel plant in Sakai City, Osaka Prefecture. The facility will be situated on approximately 440,000 square meters of land, representing about 60% of the Sharp Sakai Plant's total area, with a total floor area of 750,000 square meters.
SoftBank aims to launch full-scale operations of the data center in 2025, with an initial power capacity of 150 megawatts. The company plans to significantly increase this capacity to over 400 megawatts in the future. Construction is targeted to begin around autumn 2024.
The data center is intended for SoftBank's own generative AI development and other AI-related businesses. Additionally, SoftBank plans to offer the facility to universities, research institutions, and businesses to meet diverse AI usage needs. The company is also considering the use of clean energy sources to minimize the data center's environmental impact.
This agreement also opens the door for potential future collaborations between SoftBank and Sharp in AI-related businesses.