Key facts
- Promise Robotics said the $25 million Series B was led by White Star Capital, with Horizons Ventures, Radical Ventures and the Public Sector Pension Investment Board participating.
- CEO Ramtin Attar said the funding is for the technology platform, not for building factories.
- Promise said it has more than 2,000 housing units under contract across three markets.
- Attar said installation costs fell to about C$4.50 per square foot from about C$9 after Promise built its own installation workforce.
- Promise is setting up its Phoenix operation in a 16,000-square-foot leased warehouse, Attar said.
- Attar said Promise's production capabilities cover roughly 15% to 20% of construction activity, depending on market and components.
Promise Robotics announced a $25 million Series B financing round on November 17, 2026, led by White Star Capital with participation from Horizons Ventures, Radical Ventures and the Public Sector Pension Investment Board, HousingWire TBD reported.
The round follows a multiyear commercial agreement under which Promise will support production of more than 1,250 homes for D.R. Horton, which the report describes as the largest US homebuilder. Promise operates production facilities in Calgary and Nisku, Alberta, and says it has more than 2,000 housing units under contract across three markets. D.R. Horton is preparing to bring its first US manufacturing facility online in Phoenix in 2027, according to the report.
Co-founder and CEO Ramtin Attar said the money is meant for the technology platform rather than for factories. "It's not for funding factories; it's for funding the platform," Attar said. He said the Phoenix operation occupies a 16,000-square-foot leased warehouse requiring almost no tenant improvements, and that the same two robots producing homes in Calgary were moved to Phoenix two weeks before the report.
Attar said installation costs averaged about C$9 per square foot when Promise used outside contractors and fell to about C$4.50 after it developed its own installation workforce. He said the company's production capabilities cover roughly 15% to 20% of construction activity depending on market and components, and that it is working to raise that share to about 40%.
The report says Promise has not publicly disclosed factory-level profitability, capital requirements per deployment or the utilization rates needed to support debt repayment.