Key facts
- Data centers have requested about 34 GW of grid capacity in Norway, above national peak demand of about 25 GW.
- Only 0.8 GW is connected, 4.2 GW holds reserved capacity, 10.8 GW is in the queue and 18 GW is at inquiry stage.
- Statnett stopped granting reservations and approving facility functionality under the fos § 14 rule while it sets requirements.
- Projects with reserved capacity keep their place but still need approval before connecting, and existing connections are unaffected.
- Norway has six operating crypto data centers with about 0.2 GW combined, and new crypto sites will not be permitted.
- Rystad Energy projects Norway's net power exports could fall 71%, from 14.3 TWh in 2027 to 4.1 TWh in 2030.
Norway's transmission system operator Statnett paused new grid reservations for data centers on November 9, 2026, the same day the government announced a licensing scheme that will keep out new crypto mining. The halt will last until at least August 2027, when a new system is set to come into effect.
Data centers have asked for about 34 GW of grid capacity in Norway, above national peak demand of about 25 GW. Only 0.8 GW is connected, 4.2 GW holds reserved capacity, 10.8 GW is in the queue and 18 GW is still at the inquiry stage.
Statnett stopped granting new reservations and approving facility functionality under the Regulation on System Responsibility (fos) § 14 rule while it sets functional requirements for data centers. These will cover when facilities must stay connected during disturbances, how quickly their load may change and how to limit grid fluctuations. Projects with reserved capacity keep their place but still need approval before connecting, and existing connections are not affected.
About half of the queue has asked for power by the end of 2028. With no new reservations until August 2027 at the earliest, and grid build-out still to follow, those dates look out of reach for established operators and newcomers alike, according to the report.
Norway has six operating crypto data centers with about 0.2 GW combined. Under the licensing scheme, new crypto sites will not be permitted, and existing ones cannot get more grid capacity and could face restrictions once transitional arrangements expire. Some operators are already converting to AI.
Hydro supplies about 90% of Norway's power. Under normal hydrology, rising demand from data centers and other consumers could cut Norway's net exports by 71%, from 14.3 terawatt-hours in 2027 to 4.1 TWh in 2030, according to Rystad Energy. In a dry year, Norway could become a net importer and winter prices could reach about €290 per megawatt-hour.