Key facts
- Indonesia's energy ministry (ESDM) is accelerating medium-rank coal supply contracts for state-owned power plants on the Java grid.
- Rolling blackouts have occurred in the region over the past two weeks.
- Power plants are operating at reduced capacity due to shipments of lower-rank coal.
- A cross-sector procurement team has been formed to ensure adequate supply of coal with a calorific value of GAR 5,200 kcal/kg.
- Medium-rank coal has been secured from Kaltim Prima Coal, Indo Tambangraya Megah (ITMG), and Bukit Asam.
- Two baseload independent power plants in Cilacap and Pancitan are being reconnected after technical issues.
Indonesia's energy ministry (ESDM) has expedited the signing of supply contracts for medium-rank coal to be used in state-owned coal-fired power plants on the Java grid. This action is a direct response to rolling blackouts experienced in the region over the past two weeks.
The issue stems from consistent coal deliveries, but with a composition primarily of lower-rank coal. This mismatch in coal specifications has led to power plants operating at reduced capacity, according to an ESDM official.
To rectify the situation, ESDM has established a cross-sector procurement team tasked with ensuring a sufficient supply of coal with a calorific value (CV) of GAR 5,200 kcal/kg for the affected plants. Medium-rank coal shipments have already been secured from major producers including Kaltim Prima Coal, Indo Tambangraya Megah (ITMG), and the state-owned Bukit Asam. This coal will be blended with lower-grade coal to enhance plant efficiency and restore output.
Several plants have been identified as experiencing shortages of GAR 5,200 kcal/kg coal, including Pelabuhan Ratu, Lontar, Labuan, Suralaya units 1-8, Jawa 7, 9 and 10, Indramayu, Paiton units 1, 2, and 9, Rembang, Pacitan, and Tanjung Awar-Awar.
Concurrently, state-owned utility PLN is working to bring two baseload independent power plants in Cilacap and Pancitan back online after they were disconnected due to technical issues. The combination of these technical outages and the reduced output from coal plants burning lower-grade coal resulted in a power deficit of 2GW, prompting PLN to implement load shedding for grid stability and causing the rolling blackouts. One of the disconnected power plants has been reconnected, with the other expected to be back online within the week.