Key facts
- TSL, formally Tonroe Group, decided to leave after failing to agree terms with Agratas, according to three sources.
- Two sources said the failure to reach agreement stemmed from disagreements over the project's timeline and cost.
- TSL is expected to leave the site within two or three months, with no other main build contractor lined up.
- Agratas said it is on track to meet customer requirements and that supplier partners are supporting it well.
- The UK government has pledged £380 million in support for the factory, and not all of the subsidy has been paid out.
- Agratas has not pushed back its latest target of a January 2028 start of production.
Agratas's £5.2 billion electric vehicle battery gigafactory in Bridgwater, Somerset, has lost its second lead building contractor in five months after construction specialist TSL decided to leave the project, according to three sources. TSL, formally known as Tonroe Group, could not agree terms with Agratas. Two sources said the disagreement concerned the timeline and cost of the project.
TSL is expected to leave the site within two or three months, leaving no other main build contractor lined up. NG Bailey, the project's mechanical, electrical and plumbing contractor, is seen as one option to take over the entire build. The issues resemble those with TSL's predecessor, Sir Robert McAlpine, which Agratas fired at short notice in June; one source said discussions over the terms of its departure remain ongoing.
An Agratas spokesperson said: "We are on track to meet our customer requirements." The spokesperson added that the Somerset site is a large and complex industrialisation project and that supplier partners are supporting the company as it prepares for the facility's launch phase. Agratas has not pushed back its latest target of a January 2028 start of production.
Tata announced the gigafactory in 2023, aiming for a 2026 start of production with as many as 4,200 employees, before pushing the date back to 2027. The UK government has pledged £380 million in support for the factory, and not all of the subsidy has yet been paid out. Agratas and Jaguar Land Rover, the intended customer for the batteries, are both part of Tata Group.
Morale within Agratas has been affected by a decision to relocate some workers from Coventry to Somerset, about 120 miles away, two sources said. Some of those workers are expected to take redundancy rather than move, continuing a stream of senior staff departures in recent months, according to the same two sources. Some Agratas managers traveled to India in the week of the report to share experience with counterparts at the company's Sanand site and discuss the UK situation.
The shell of the Bridgwater building is mostly complete, and National Grid has started work on the electricity substation that will supply power to the plant. JLR has secured batteries from other suppliers, so its plans to increase sales of new electric Land Rovers and Jaguars will not be affected, though those initial cars will not have British-made batteries. TSL, JLR and NG Bailey declined to comment or were approached for comment.