Vietnam's Long Thanh airport nears opening amid construction push, airline concerns

Created at 10 Sep · 2:06 AM1 source↑ Market-relevant
IN SHORT

Vietnam is preparing for trial operations at its new Long Thanh International Airport this month, aiming for commercial flights by late 2026. Despite a significant construction acceleration, challenges remain regarding fees and airlines' willingness to relocate from the congested Tan Son Nhat International Airport.

Key Numbers

2026target year for phase one opening
25 millioninitial annual passenger capacity
1.2 million tonsinitial annual cargo capacity
40 kilometersdistance east of Ho Chi Minh City
9,000+manpower mobilized for the project

Who's Involved

Long Thanh International Airport
new hub airport preparing for trial operations
Tan Son Nhat International Airport
current congested gateway for Ho Chi Minh City
Airports Corporation of Vietnam
state-controlled operator overseeing project components
Pham Minh Chinh
Prime Minister who instructed completion by Q3 2026
Vietnam's Long Thanh airport nears opening amid construction push, airline concerns

↳ Why This Matters

The successful launch of Long Thanh International Airport is crucial for Vietnam's economic growth, tourism, and its ambition to become a regional aviation hub. Delays or operational challenges could impact the country's infrastructure development goals and its ability to handle increasing air traffic.

Key facts

  • Vietnam is preparing for trial operations at Long Thanh International Airport this month.
  • Long Thanh International Airport is designed to become Vietnam's largest and most modern aviation hub.
  • Phase one includes a passenger terminal, a runway, and core technical facilities.
  • The airport's initial capacity is planned for 25 million passengers and 1.2 million tons of cargo annually.
  • Commercial flight services are targeted for the fourth quarter of 2026.
  • The project has faced delays in land acquisition and package tendering.

Vietnam is nearing the start of trial operations for its new Long Thanh International Airport, a massive infrastructure project intended to alleviate congestion at Ho Chi Minh City's current gateway, Tan Son Nhat International Airport. Despite a significant acceleration in construction, with over 9,000 workers and military engineering units mobilized, the project faces challenges in meeting its ambitious 2026 opening targets. Prime Minister Pham Minh Chinh has instructed that key construction stages be fully completed by the third quarter of 2026, with commercial flight services aiming for the fourth quarter. The first phase of Long Thanh is designed to handle an initial capacity of 25 million passengers and 1.2 million tons of cargo annually, featuring a world-class terminal and a runway capable of accommodating large commercial aircraft. However, emerging concerns include potential delays due to complex fit-out and systems integration, cost pressures from fluctuating material prices and contractor performance, and airlines' reluctance to shift operations from Tan Son Nhat due to fee disputes and network planning complexities. The project is viewed as a symbol of Vietnam's growth ambitions and is central to its tourism and investment strategies through 2030.

Frequently asked questions

Long Thanh International Airport is designed to become Vietnam's largest and most modern aviation hub, intended to relieve chronic crowding at Tan Son Nhat International Airport and anchor the wider Southern Key Economic Region.

Phase one includes one passenger terminal, a runway, and core technical facilities, with an initial capacity to process 25 million passengers and 1.2 million tons of cargo annually.

The project faces challenges including potential timeline slippage, cost pressures, contractor performance issues, and airlines' reluctance to move flights due to fee disputes and network planning.

What Happens Next

01Trial operations to begin this month.
02Phase one construction to be fully completed by the third quarter of 2026.
03Commercial flight services targeted for the fourth quarter of 2026.

Discussion

0 / 1000

Loading comments…

How It Developed

Construction ramped up from late 2023 on Long Thanh International Airport.
Prime Minister Pham Minh Chinh instructed key construction stages to be completed by the third quarter of 2026.

Sources

T1
Vietnam's new hub airport nears takeoff but airlines slow to get on boardNikkei Asia
T2
Long Thanh Airport Opening Date: Latest 2026 Timeline | evisas vietnamevisasvietnam.com
T2
Long Thanh Airport Opening Timeline: Vietnam Speeds Projecttheasianaffairs.com
T2
Vietnam's Long Thanh Airport Faces Fresh Delay Risksthetraveler.org

Related Stories

Hong Kong, Kazakhstan Sign Transport MOU, Discuss Low-Altitude Economy
9 Sep · 9:10 AM
Hong Kong Aims for Biomedicine Hub Status in New Five-Year Plan
9 Sep · 9:36 AM
Seoul aims for global top 3 city status by 2030 with $64.3 billion investment
10 Sep · 2:16 AM
China accelerates drug price talks as commercial insurance list shrinks
10 Sep · 2:41 AM
South Korea Launches AI Diplomacy Division, Eyes Japan Partnership
9 Sep · 8:11 PM