Key facts
- Alaska LNG developer Glenfarne claims shipping costs to Asia from Alaska's North Slope will be at least 65% cheaper than from the U.S. Gulf Coast.
- The project's estimated cost is $44.5 billion to $54.5 billion, with delivery costs around $1.4 billion per MTPA.
- Glenfarne has secured customers for 13 million tons per year of LNG and needs 16 million tons annually for financing.
- President Trump cited a $200 billion South Korean investment package that he said would help finance the Alaska LNG project, though Seoul indicated its role is not finalized.
The developer of the proposed Alaska LNG project stated that its access to stranded natural gas and shorter shipping routes to Asia will make it competitive with U.S. Gulf Coast rivals, despite significant infrastructure costs. Glenfarne, the project's developer, argues that the comparison of upfront spending is misleading because it includes pipeline and gas treatment infrastructure.
Tim Fitzpatrick, communications director for Glenfarne, said on Sunday that the cost of shipping gas to Asia from Alaska's North Slope would be at least 65% cheaper than shipping LNG from the Gulf Coast. The project, which would move gas from Alaska's North Slope through an 800-mile pipeline to a liquefied natural gas export plant in southern Alaska, has an estimated cost of $44.5 billion to $54.5 billion. This translates to roughly $2.2 billion to $2.7 billion per million tons per annum (MTPA) of LNG capacity, which is higher than many recently approved Gulf Coast developments.
Glenfarne contends that the Alaska LNG project entails about $1.4 billion per MTPA in delivery costs. The company has identified customers for 13 million tons per year of LNG and requires 16 million tons annually to support project financing. President Donald Trump had previously stated that South Korea would help finance the Alaska LNG effort as part of a $200 billion package of investment in U.S. projects, but Seoul has indicated that its role in the Alaska project is not yet set.