Key facts
- SK Hynix's first Yongin fab, Y1, was about 89% complete roughly 20 months after construction began.
- About 20,000 workers are on site daily, rising to 25,000 to 26,000 including support facilities, per E-Daily.
- Cluster infrastructure was about 95.5% complete, with a target of partial completion in February, per SK Eco Plant's Cho Byung-wook.
- The cluster spans about 1.26 million pyeong (4.15 million square meters), with four fabs planned by 2033.
- SK Hynix plans to invest 35.2 trillion won in the second fab, Y2, breaking ground in July and opening its first cleanroom in June 2029.
- About 55 materials, parts and equipment companies are due to move into a roughly 140,000-pyeong partner complex.
SK Hynix is building its largest semiconductor manufacturing complex in Yongin, about a 90-minute drive from Seoul, with the first fabrication plant, Y1, about 89% complete roughly 20 months after construction began in late February 2025. The company has committed about $450 billion to the four-fab site, which it says is intended to keep pace with demand for artificial intelligence computing.
Cho Byung-wook, a team leader at SK Eco Plant, said overall infrastructure at the cluster was about 95.5% complete, with a target of partial completion in February. The first fab is planned to stand about 150 meters tall, equivalent to a 50-story apartment building, and will house six cleanrooms across three floors, with two on each level.
About 20,000 workers are on site each day, according to E-Daily, rising to 25,000 to 26,000 including support facilities. The cluster covers about 1.26 million pyeong, or 4.15 million square meters, roughly 1.4 times the size of Yeouido, and includes a materials, parts and equipment collaboration complex where about 55 companies are due to move in.
SK Hynix plans to invest 35.2 trillion won in the second fab, Y2, with full construction starting in July and the first cleanroom opening in June 2029. The company aims to complete the first cleanrooms of all four fabs by 2033.