Key facts
- CleanSpark held 13,530 Bitcoin at the end of September, a holding last valued at $806 million.
- CFO Gary Vecchiarelli said CleanSpark already aims to sell virtually all Bitcoin it mines to cover operating costs.
- CleanSpark attributed two-thirds of its $987 million net loss to noncash adjustments in the value of its Bitcoin holdings.
- Bitcoin fell from about $114,100 to $83,600 over CleanSpark's fiscal year, the company said.
- CleanSpark said it sold an undisclosed amount of Bitcoin since September to raise cash for expected acquisitions.
- CleanSpark said its first AI data hall in Sandersville, Georgia, remains on track for the fourth quarter of 2027.
Bitcoin miner CleanSpark is considering selling more Bitcoin than it mines each quarter to reduce treasury risk, chief financial officer Gary Vecchiarelli said on a November 24 earnings call. The company already aims to sell virtually all of the Bitcoin it mines to cover day-to-day operating costs, he said.
CleanSpark mined 1,708 Bitcoin and sold 2,102 Bitcoin in the quarter ended September 30, according to Cointelegraph's tally of the company's monthly operating updates. It ended the quarter holding 13,530 Bitcoin, a holding last valued at $806 million, and with fewer Bitcoin than it began the quarter with for the first time since at least 2024.
"We see the selling of a small amount of Bitcoin in excess of the quarterly production to be one way of de-risking," Vecchiarelli said. He added that CleanSpark would be "sensitive and very reactionary to markets" and use the capital to avoid dilution or additional debt to grow the company.
CleanSpark recorded a $987 million net loss for the fiscal year ended September 30, against net income of $364 million a year earlier. The company attributed two-thirds of the swing to noncash adjustments in the value of its Bitcoin holdings, as Bitcoin's price fell from about $114,100 to $83,600 over the fiscal year. Total revenue was $576.5 million, down 25%, and adjusted EBITDA was a loss of $304.2 million.
CleanSpark also said it sold an undisclosed amount of Bitcoin since September to raise cash for expected acquisitions, with Vecchiarelli describing the holdings as "a liquid source of non-dilutive capital." The company cut about 25,000 machines from its mining fleet in the September quarter, leaving about 200,000 in operation, and said the reduction improved energy efficiency to 14.8 joules per terahash from 15.8.
In Sandersville, Georgia, CleanSpark said its first AI data hall remains on track for the fourth quarter of 2027, and it expects to start unplugging miners at the site in late 2027 as the data center comes online, then decide whether to relocate or sell them. CleanSpark shares fell 7.5% to $5.12 on Tuesday ahead of the earnings release and were down 2.25% in after-hours trading.