Key facts
- The Federal Reserve's Inspector General found no criminal violations or misconduct in a building renovation project that experienced significant cost overruns.
- The IG report identified extensive oversight problems and mismanagement by the Fed's Board of Governors and staff.
- The renovation project's total estimated cost reached $2.4 billion, more than double the original February 2020 estimate of $921 million.
- The Federal Housing Finance Agency's (FHFA) Office of Inspector General will cut 70%-80% of its staff and discontinue investigations due to a budget reduction.
- The FHFA's OIG budget was cut to $20 million, a 64% decrease from the White House's submitted budget.
The Federal Reserve's internal watchdog has concluded that the agency broadly mismanaged an expansive building renovation project, but found no criminal violations or misconduct. The Fed's Inspector General stated that a variety of missteps by its Board of Governors and staff inflated the cost of the $2.4 billion renovation.
The board did not secure a comprehensive cost estimate at the beginning of the project, nor did it nail down a maximum overall cost, a step that could have forced the building contractor to absorb the impact of inflation, the IG said in a 120-page report. Prices spiked after construction began in 2022.
The renovation project became a high-profile flashpoint in attempts to pressure the Fed into cutting its key interest rate. Then-President Donald Trump visited the construction site last July, correcting Trump’s estimate of the project’s expected costs. Trump’s Justice Department then launched an investigation into whether Powell had committed perjury during brief testimony on the building renovation before a Senate committee. That investigation was dropped in April after a judge quashed subpoenas issued by Jeanine Pirro, the U.S. attorney for the District of Columbia.
At no point during the evaluation did the IG find reasonable grounds to believe that a violation of federal criminal law had occurred. The report said that construction costs to renovate two Fed buildings more than doubled from an original estimate of $921 million in February 2020 to $2.018 billion by December 2024. Construction is expected to last until December 2027, long past its originally slated completion date of mid-2024. Some aspects of the project criticized for being luxurious were not significant drivers of the excessive costs.
Separately, the US Federal Housing Finance Agency's (FHFA) internal watchdog warned lawmakers that it will have to cut most staff and will not be able to do its job of policing internal misconduct after the housing regulator slashed its budget. The FHFA cut the Office of Inspector General funding, aiming to bring it more in line with its peers. The IG's Acting Principal Deputy James Hodge wrote to lawmakers that the cuts would reduce the office's annual budget to $20 million, 64% less than the White House submitted to Congress, and that the office would have to cut 70%-80% of staff and discontinue investigations.
