Japan's Taketoyo plant to undergo safety revamp after fire

Created at 3 Aug · 10:56 AM1 source↑ Market-relevant
IN SHORT

Kawasaki Heavy Industries will renovate Japan's Taketoyo coal- and biomass-fired power plant's fuel-conveying facilities to prevent fires and explosions. The work, aimed at improving dust collection and installing fire monitoring equipment, is expected to be completed by June 2028.

✉Newsletter

PiQ Daily

Pick your topics. Get only what matters, on your cadence.

Key Numbers

1.1GWTaketoyo power plant capacity
1,070MWTaketoyo power plant capacity
June 2028Renovation completion target
January 2024Date of fire incident
January 2025Plant resumed operations
17%Previous biomass rate
8%Planned biomass rate

Who's Involved

Kawasaki Heavy Industries (KHI)
Engineering firm carrying out plant renovation
Jera
Holding company and Japan's largest power producer

↳ Why This Matters

The renovation of the Taketoyo power plant addresses safety concerns following a fire incident, aiming to ensure more reliable operation of biomass co-firing and contribute to Japan's greenhouse gas emission reduction goals.

Key facts

  • Kawasaki Heavy Industries will renovate Japan's 1,070MW Taketoyo coal- and biomass-fired power plant.
  • The renovation focuses on wood pellet fuel-conveying facilities to enhance safety.
  • The project includes improving dust collection and installing fire monitoring equipment.
  • The work is scheduled for completion by June 2028.
  • The plant suffered a fire in January 2024, causing it to halt operations until December.
  • Jera plans to reduce the biomass co-firing rate to 8% from the previous 17%.
  • Kawasaki Heavy Industries (KHI) will undertake renovation work at Japan's 1,070MW Taketoyo coal- and biomass-fired power plant. The company will focus on the wood pellet fuel-conveying facilities at the Taketoyo No. 5 unit to prevent fires and explosions by improving dust collection and installing fire monitoring equipment. The renovation is slated for completion by June 2028.

    The Taketoyo plant began co-firing coal and biomass in August 2022, utilizing approximately 500,000 tonnes per year of wood pellets at a 17% biomass rate. However, a fire, seemingly caused by a dust explosion, occurred in January 2024, forcing the plant to halt operations until December. Following repairs, the plant restarted in January 2025, operating solely on coal.

    Currently, the power plant in Aichi prefecture operates only during peak electricity demand periods in summer and winter to reduce greenhouse gas emissions. Jera, Japan's largest power producer by capacity, initially planned to restart biomass co-firing in the first quarter of 2027 but has postponed this to June 2028. When operations resume, Jera intends to lower the biomass rate to 8% from the previous 17% to enhance safety.

    Frequently asked questions

    The Taketoyo power plant has a capacity of 1,070MW, or 1.1GW.

    The fire in January 2024 was seemingly caused by a dust explosion.

    Jera plans to decrease the biomass rate from 17% to 8% to enhance safety when operations resume.

    What Happens Next

    01Renovation work to be completed by June 2028.
    02Biomass co-firing operations to resume in June 2028.

    Get the newsletter.

    Pick the topics you actually care about. We'll email when there's news worth your time, on the cadence you choose. Cancel any time from your account.

    Cadence
    CME Headlines
    • Amendments to Rule XXX101. (Contract Specifications) and XXX102.E. (Termination of Trading) of the LNG North West Europe Marker (Platts) Futures and the LNG North West Europe Marker (Platts) BALMO Futures and Temporary Suspension of Trading and Clearing of Previously-Listed Contract Months
      31 Jul · 11:30 PM
    • OPEC+ decision and Nonfarm Payrolls in focus for next week.
      31 Jul · 9:03 PM
    • OPEC+ decision and Nonfarm Payrolls in focus for next week.
      31 Jul · 9:03 PM

    How It Developed

    Kawasaki Heavy Industries will renovate the Taketoyo power plant's wood pellet fuel-conveying facilities.
    The renovation aims to prevent fires and explosions by improving dust collection and installing fire monitoring equipment.
    The Taketoyo plant experienced a fire in January 2024, leading to a halt in operations until December.
    The plant resumed operations in January 2025, burning only coal.
    Jera plans to decrease the biomass rate from 17% to 8% upon resuming biomass co-firing operations.
    Biomass co-firing operations are now scheduled for June 2028, postponed from Q1 2027.

    Sources

    T1
    Japan's 1.1GW Taketoyo biomass-coal plant to revampArgus Media

    Related Stories

    Australia's NT seeks federal backing for Gove fuel hub
    3 Aug · 10:56 AM
    Uganda's Stack Carbon signs major carbon credits deal
    3 Aug · 6:06 AM
    Indian polyolefin importers wary on Middle East risks
    3 Aug · 11:51 AM
    China Buys 13 U.S. Soybean Cargoes Amid Price Decline
    3 Aug · 9:51 AM
    Tyson Foods Cuts Annual Profit Forecast Amid Tight Cattle Supplies
    3 Aug · 11:41 AM